On this page you will find which road works are in progress within the built-up area in municipality of Voorne aan Zee , how long they will last and any detour.

Brielle

Stedin installation of electrical cables Maarland North Side/Dijkstraat

When 

  • Monday, February 16 through Friday, March 20.

Where

  • Maarland North Side and Dijkstraat in Brielle.
  • Stedin is upgrading the electrical cables. They are making the cables strong enough to transport the amount of electricity that the neighborhood demands and feeds back into the grid, without power outages.
  • Local residents have received a letter from Stedin with more information. 

Detour 

  • In Maarland-Noordzijde, from house numbers 1 to 51, the road will become one-way. No parking signs will be placed along the quay. The charging stations and disabled parking spaces will remain accessible.
  • Homes are always accessible, possibly via a temporary walkway or plank.

Contact

  • If you have any questions or complaints, please contact Stedin. You can do so on working days between 8 a.m. and 5 p.m. You can contact us via WhatsApp on 06 46 96 39 63 or via our customer service department on 088 896 39 63.

Hellevoetsluis

Renovation of the Marinebuurt neighborhood

When 

  • Work will commence on Monday, November 24, 2025, and continue until Friday, November 13, 2026. 

Where

Contact

  • Questions about the work can be directed to the contractor Van Doorn, Mr. Kentie, environmental management officer, telephone number 0345 57 11 41 or email nl.

Improvements to the roundabout at Evertsenplein

When 

  • From Monday, February 2, through Friday, April 3. 

Where

  • The roundabout at Amnesty Internationallaan/Rijksstraatweg, near Evertsenplein.
  • We are making the roundabout safer by moving the crossings further back.
  • In April 2024, the bicycle crossing on the north side will be constructed further away from the roundabout. We are now doing the same with the other three crossings.

Detour

  • The work will be carried out in phases.
  • During phase 1 (February 2 through February 13) and phase 2 (February 16 through March 13), cars, trucks, and motorcycles will be able to pass through as usual. Pedestrians and cyclists will be diverted. The diversion will be indicated by signs.
  • During phase 3 (March 16 through April 3), the roundabout will be closed on weeknights. Traffic will be diverted.
  • For the schedule and detours, please refer to the page Improvement of the roundabout at Evertsenplein

Contact

  • Contractor Van Gelder is carrying out the work. If you have any questions about the work being carried out and the diversion route, please contact Van Gelder's environmental managers: Liesbeth van Dijke on +31 (0) 6 81 93 84 92 and Francis Danen on +31 ( 0)6 14 36 40 70.
  • Van Gelder shares information and news via the BouwApp. Download the BouwApp from the App Store or Google Play Store. Search for "Roadworks Voorne aan Zee" in the app and follow it for the latest updates.

Bicycle crossings Nelson Mandelalaan

When 

  • From Monday, April 20, through Friday, May 15. The work will be carried out in phases. 

Where 

  • The bicycle crossings on Nelson Mandelalaan, Dorpsweg, and Bonseweg in Hellevoetsluis are being made safer.
  • We are removing the existing thresholds and installing a raised platform with traffic lights. Both crossings will be coated in yellow. This has a slowing effect.
  • In phase 1 (Monday, April 20 through Thursday, April 30), Van Gelder will carry out work on the bicycle crossing at Bonseweg. At the same time, the bicycle path from Bonseweg to the Dijkweg intersection will be repaved.
  • In phase 2 (from Friday, May 1, through Friday, May 15), Van Gelder will carry out work on the bicycle crossing at Dorpsweg. 

Detour

  • During the works, Nelson Mandelalaan will be closed to traffic between the Dag Hammarskjöldlaan roundabout and the Moeder Teresalaan roundabout.
  • Through traffic will be diverted via Kanaalweg Westzijde.
  • The Berkman gas station remains accessible.
  • The work will be carried out at each crossing point.
  • Cyclists will be diverted via one of the two crossings. In phase 1 (Monday, April 20 through Thursday, April 30), cyclists can use the Dorpsweg crossing. In phase 2 (Friday, May 1 through Friday, May 15), cyclists can use the Bonseweg crossing. 

Contact

  • Contractor Van Gelder is carrying out the work. If you have any questions about the work or the diversion route, please contact Liesbeth van Dijke, Van Gelder's environmental manager, on +31 (0)6 81 93 84 92.
  • Van Gelder shares information and news via the BouwApp. Download the BouwApp from the App Store or the Google Play Store. Search for “Roadwork Voorne aan Zee in the app and follow for the latest updates.

Oostvoorne

Rockanje

Redesign of Jupiter Avenue and surrounding area

When 

  • From Monday, March 9, until the end of December. 

Where

  • Jupiterlaan, Plutostraat, Sagittastraat, Orionstraat, Librastraat, Wega, and part of Van Leijdenstraat in Rockanje.
  • We are starting with the construction of a new rainwater sewer. This means that rainwater will not end up in the sewage system, but will be discharged into the groundwater or the canal. All drainage wells on the roadway will be connected to this sewer.
  • After installing the new sewer system, the street will be closed again using the same materials. The sewer trench must settle for three months (to prevent subsequent subsidence of the street).
  • Then we will start redesigning the neighborhood. Among other things, the paving will be completely redone. We will use new materials for this. New shrubs and trees will also be planted in the neighborhood.

Detour 

  • During the work, some homes will be more difficult to reach by car. Residents will always be able to reach their homes on foot.

Contact 

  • Contractor Kraaijeveld is Voorne aan Zee this work on behalf of the municipality Voorne aan Zee . If you have any questions or complaints, please contact Marjolein Kraaijeveld of contractor Kraaijeveld by email nl or by telephone on 0180 61 35 22

Heveringseweg / Boomweg

The Hollandse Delta Water Authority is going to tackle the section running from Oostvoorne to Rockanje. This concerns the Heveringseweg, Verlengde Lodderlandsedijk, Boomweg, and Vleerdamsedijk. The section will be redesigned to meet sustainable safety standards, and major maintenance will be carried out on some parts. 

More information about the work and the schedule can be found on the project website of the Hollandse Delta Water Authority.

Municipality of Voorne aan Zee general

BuildingApp

Contractor Van Gelder is carrying out Voorne aan Zee on the road network in our municipality on behalf of the municipality Voorne aan Zee . This mainly involves asphalting work. This work may cause temporary inconvenience to road users and local residents. Road diversions may also be put in place in connection with the work.

Stay informed through the ConstructionApp

Contractor Van Gelder uses the BouwApp to keep residents informed. Would you like to stay up to date on the planning, progress, and any diversions related to the (maintenance) projects? Download the BouwApp from the App Store or Google Play store. Search for "Wegwerkzaamheden Voorne aan Zee" in the app and follow it for the latest updates.

We thank you for your understanding and cooperation.

Learn more about road works

Do you have a question or complaint about a road? If so, please contact the road manager directly.

The roads in the municipality of Voorne aan Zee are managed by different government organizations. The Department of Public Works manages the N57 and the A15. The province of Zuid-Holland manages the N218, N494, N496 and the N497. All other (polder) roads are managed by the Hollandse Delta water board. The municipality manages the roads within the built-up area. You can look up who the road administrator is via the Rijkswaterstaat website if you are in doubt.