Voorne aan Zee Housing Authority is building 12 social housing units and 12 mid-range rental units at Burgemeester Bolwidtweg 12. The building permit has now been issued, and construction is set to begin shortly. The contractor is expected to complete the units by the end of November 2027. 

The De Ruy apartment complex is intended for seniors aged 65 and older. It will consist of a single four-story building. All units will have two bedrooms. Woonbedrijf Voorne aan Zee will lease and manage the units.

Photo: final design

The listings for the various types of housing were published on Woonnet Rijnmond on Monday, November 2. The listings were online for two weeks. Woonbedrijf’s rental staff are currently reviewing which applicants are eligible based on the “ Requirements ” and the applicable allocation rules, and whether the applicants meet the “ Requirements .” Afterward, the housing units will be allocated.

Contact and more information 

Do you have any questions? Call Woonbedrijf at 14 0181 (Monday through Thursday between 9:00 a.m. and 11:00 a.m.). Or send an email to huurzakenwoonbedrijf@voorneaanzee.nl.

You can also sign up for Bouwbedrijf Schrijver's newsletters. To do so, send your email address toderuy@bouwbedrijfschrijver.nl.

Download the ConstructionApp

Schrijver Construction uses the BouwApp. Through this app, they keep you informed about the work and other developments. You can also easily contact them or ask questions via the BouwApp.

Download the BouwApp from the App Store or the Google Play Store. Search for the project “De Ruy Oostvoorne Apartment Complex” in the app and click “Follow.” Turn on notifications so you’ll receive messages right away.

Updates

Registration has been delayed

In April 2026, it became clear that construction of the De Ruy apartment complex would begin later than planned. The units were not listed on WoonnetRijnmond in September 2026, as we had previously hoped.

Environmental permit application submitted

On November 25, 2025, the environmental permit application was submitted to the municipality. Interested parties were able to submit comments or objections. The processing period was extended by six weeks because additional information was required. In the meantime, Schrijver Construction continued to prepare for construction. The homes were expected to be offered for sale in March 2026. The exact date depended on the approval of the environmental permit application.

Bush strolling

On Saturday, November 1, 2025, residents of Voorne aan Zee were allowed to dig up plants from the park on the Ruy in Oostvoorne for their own gardens. The plants in the village park had to be removed to prepare the land for construction. These were high-quality perennials, such as asters and geraniums. At 10:00 a.m., Aldermen Daan van Orselen and Robert van der Kooi, together with the design manager from Bouwgroep Schrijver, gave the go-ahead. Residents had until 2:00 p.m. to use their own tools to dig up a few (up to fifteen) plants per address and plant them in their own gardens.

Photo of wandering through the bushes

Construction Contract Signed

With the signing of a construction contract on Tuesday, June 10, 2025, a major step was taken toward the construction of 12 social housing units and 12 mid-range rental units on Burgemeester Bolwidtweg in Oostvoorne. Alderman Daan van Orselen of Woonbedrijf Voorne aan Zee and Landré Schrijver, director of Bouwgroep Schrijver, signed the agreement for 24 age-accessible apartments. The current housing stock will be preserved as much as possible, as will the green belt and the existing walking paths between the De Brielsche Hoeck apartment complex and the apartment complex on Elisabethhof.

Photo taken at the moment the construction contract was signed.

Preparations have begun

We began preparations for the De Ruy apartment complex in the summer of 2025. We are building a single four-story residential building with apartments for seniors aged 65 and older. All apartments have two bedrooms. Het Woonbedrijf rents out and manages the apartments.

On Monday, November 2, we posted the listings for the various types of homes on Woonnet Rijnmond. They remained online for ten days. 

We will now review the applicants' information. We will allocate the housing units based on the Requirements and the allocation rules.

The parking spaces and about half of the park will remain as they are now. We expect the homes to be completed by the end of November 2027.