Oostvoorne center area redevelopment
An urban design/landscape vision plan has been created for the center of Oostvoorne. This plan states that Oostvoorne wants to have a lively and inviting village center. To make this possible, a number of roads in the center have already been redesigned. The next phase of the redevelopment will start September 1, 2025.

Citizen Participation
Through a process with residents (citizen participation process), a new design for the public area was created. In making this design, the goal was to make the center attractive and safe.
Planning and Phasing
Work will begin on September 1, 2025 and will be carried out in phases. For each phase, roads will be closed. Residents and business owners will be able to access their premises on foot during the closure. The work is expected to last until the end of November 2025.

This image shows a Map with a phased schedule of road works in Oostvoorne. The Map is divided into different colored zones, each indicating a specific phase of the works, with corresponding dates.
Description of phasing:
- Phase 1 (green): Mayor Lette Road "North," from Sept. 1 through Sept. 11.
- Phase 2 (brown): Burgemeester Letteweg "South," from Sept. 12 through Sept. 24.
- Phase 3 (blue): Station Road intersection on Sept. 25.
- Phase 4a (purple): intersection Church Square - Burgemeester Letteweg, from Sept. 26 to 29.
- Phase 4b (light blue): Church Square "South," from Sept. 30 through Oct. 10.
- Phase 5 (gray): Church Square "North," from Oct. 13 through Oct. 23.
- Phase 6 (red): intersection Church Square - Court Avenue on Oct. 24.
- Phase 7a (dark red): intersection Church Square - Mildenburg Avenue, Oct. 27 and 28.
- Phase 7b (orange): Mildenburg Avenue 'North,' from Oct. 29 through Nov. 13.
- Phase 8 (blue-gray): Mildenburg Avenue 'south' from Nov. 14 to 28.
A green zone has also been designated at Church Square 'North' for "additional parking" during the work.
Staying informed
Contractor GKB Realization is performing the work. Would you like to stay informed about the current work? Then download the GKB - communication app.
Here's how it works:
- Download the GKB Communication app from the App Store (iOS) or Google Play Store (Android).
- Open the app
- Click on 'View our projects'
- Select the project Oostvoorne Center Area